General Information
COMMERCIAL STRUCTURES (INCLUDING
ADDITIONS)
- Completed BUILDING permit application.
- Six sets of stamped plans and specifications (seven sets if
food establishment), including floor plan, plumbing, electrical,
mechanical, wall sections, elevations, interior finishes, etc.
- Six Plats of Survey indicating proposed work.
- Three sets of stamped civil engineering drawings including
water, sewer, grading and pavement details for new structure.
RESIDENTIAL
STRUCTURES (INCLUDING ADDITIONS)
- Completed BUILDING permit application.
- Five sets of stamped plans and specifications, including floor
plan, plumbing, electrical, mechanical, wall sections, elevations,
interior finishes, etc.
- Five Plats of Survey indicating proposed work.
- Three sets of stamped civil engineering drawings including
water, sewer, grading and pavement details for new structure.
DECKS
- Two plats of survey indicating size (drawn to scale) and
location.
- Completed BUILDING permit application.
- Two sets of detailed plans, showing materials used and
framing, including dimensions, railing details, elevations, and
steps.
- Postholes must be 42" deep.
- Design minimum 40lbs live load.
- Railings required if deck exceeds 30" in height above grade.
- Decks shall be setback 5 from all lot lines and cannot be
built on the easements.
DEMOLITION
- Completed BUILDING permit application.
- Two Plats of Survey indicating structure to be removed.
- Submit copy of Cook County EPA permit.
- Submit cut-off letters from all utility companies.
- Dumpsters may be temporarily located on private property.
DRIVEWAYS
- Two Plats of Survey indicating location, length and width.
- Completed DRIVEWAY permit application.
- If working in the ROW, a copy of City specifications will be
attached as part of approved permit.
- Maximum width of driveway at sidewalk is 25 with a 3 flare
to the curb cut on both sides. Maximum width of driveways in
commercial or industrial areas is 35.
- On corner lots driveways shall be set back 10 from sidewalk
abutting corner of lot.
- Driveways shall not exceed 50% of required front yard.
- Cover seal does not require permit.
- Concrete 4" concrete over 4" CA-6 crushed stone.
- Asphalt 2" asphalt over 6" CA-6 crushed stone.
- License agreement for pavers in the apron / ROW.
ELECTRIC
- Submit completed ELECTRIC permit application detailing nature
of work to be done.
ELEVATOR
- Completed BUILDING permit application.
- Three sets of plans and specifications.
FENCES
- Two Plats of Survey indicating location and height of fence.
- Completed FENCE permit application.
- 6 maximum height in side and rear yards, except corner lots.
- Fences in front yards shall not exceed 4 in height and shall
be 50% open. Front yard fences shall also be uniform in height,
material, type and design.
- Enclosed fenced areas shall be provided with a gate.
- Fence posts shall be on owners side of fence.
- Fences shall not exceed 8 in height in commercial and
industrial areas.
- Barbed wire fences are not permitted without special approval
of the Zoning Administrator.
GARAGES
- Two Plats of Survey indicating location of structure and
setbacks from property lines and dwelling unit.
- Two sets of detailed plans.
- Completed BUILDING permit application.
- 5 setback required from building wall to lot lines.
- Maximum garage size is 24 x 30. Maximum height allowed is
15.
- Garages shall be set back 5 from dwelling; garages that are
set back less than 5 must comply with the fire rating provisions
of the Building Code.
- Electric is required in all garages.
- Combination of all sheds and garages shall not exceed 50% of
the required rear yard.
- Hard surface required to garage apron. If necessary, apply for
separate DRIVEWAY permit.
HEATING/AIR
CONDITIONING
- Completed MECHANICAL permit application. Permit required for
new or replacement.
- Electrical work requires licensed electrician.
LAWN SPRINKLER (UNDERGROUND)
- Completed PLUMBING permit application.
- Minimum of two Plats indicating proposed head locations.
- If there are heads in ROW, City Council must approve. Submit
$220 application fee along with signed License Agreement, request
for License Agreement, ROW permission form. These forms are
available in Planning and Zoning.
- Licensed plumber must perform work.
PATIOS AND
OTHER MISCELLANEOUS CONCRETE
-
Two copies of Plat of Survey indicating
location and size of patio, drawn to scale, or locating other
concrete work to be done.
-
Completed BUILDING permit application.
-
Concrete patios may not extend more than 25
from dwelling.
-
Patios are allowed only behind the house.
-
Concrete shall be a minimum of 4" below top of
building foundation and pitch away from building at Ό" per foot.
Drainage shall not be directed onto neighbors properties.
-
Patios shall be set back 5 from property lines
and shall not be located on easements.
-
Concrete shall be a minimum of 4" thickness on
4" granular fill.
-
Paving brick permitted. Applicant to provide
manufacturers specifications on installation.
PLUMBING/SEWER
- Completed PLUMBING permit application indicating work to be
done.
ROOF
- Completed ROOF permit application.
- Maximum of 2 layers of shingles allowed.
- State of Illinois Roofing license required.
SHEDS
- Two Plats of Survey indicating location of structure and
setbacks from property lines and dwelling.
- Two sets of plans, including framing materials to be used and
anchoring system.
- Completed BUILDING permit application.
- Sheds shall be set back a minimum of 5 from property lines
and 5 from dwellings.
- Maximum shed size is 10x 12. Shed shall not exceed 15 in
height.
- No more than one shed and one detached garage may be located
on a lot.
SIDING
- Completed BUILDING permit application.
SIGNS
- Two Plats of Survey indicating location and setbacks of signs
from property lines.
- Two plans indicating detail of sign and dimensions.
- Complete SIGN permit application.
- Portable movable signs are prohibited.
- Temporary signs must be attached to building and erected for a
maximum 30 days 4 times per year with a 60-day interval between
permits. A $200.00 cash refundable bond is required.
- Copy of electricians license, if applicable.
SWIMMING
POOLS, SPAS, PONDS
- Permit is required for swimming pools, spas, ponds that are
more than 2 deep. Submit completed POOL permit application.
- Two copies of Plat of Survey required indicating location of
proposed pool drawn to scale. The pool shall not encroach on any
front or side yard. The wall of the pool shall not be less than 5
from any rear or side property line or within 10 of any street
property line. The pool must be a minimum of 10 from any overhead
wires.
- Minimum 5 high fence with self closing, locking gate around
yard OR at perimeter of pool with swing-up, locking stair.
- Show source of water and power on drawings.
- Detailed construction drawing required for in ground pools.
- Statement of proposed grading changed required on Plat.
- If spa, indicate base for spa to sit on: deck, concrete,
gravel, etc.
TANK INSTALLATION / REMOVAL (COMMERCIAL)
- Completed BUILDING permit application.
- Three sets of plans and specifications.
- State Fire Marshalls permit.
WINDOW REPLACEMENT
- Complete BUILDING permit application.
- No permit required for replacement with no framing opening
changes.
- Provide header details on framing plan.

*LICENSE AND BOND REQUIREMENTS AS ATTACHED APPLY TO ALL PERMIT
TYPES*
Updated: January 2008
Living In Des Plaines |
Your Local Government |
Your City Services
Economic Development
| Online City Reference
Desk
Search |
Site Map |
Home
Send feedback to the City by clicking
here.
Click here to report a website technical issue.
This site is best viewed in
Internet Explorer 7.0 or higher or Firefox 2.0 or higher.
City of Des Plaines
1420 Miner St.
Des Plaines, IL 60016
847-391-5300 |

This site has documents available
in PDF format. If your browser does
not have the Acrobat Reader
plug-in that is required to view
these documents, click here
to
download a free copy of this software. |
Site
Design/Development by
 |
Site
Use Policy
All information © 2008 Des Plaines, Illinois
|

|