Sidewalk, Curb and Driveway Guidelines
SUMMARY AND INTENT OF PROJECT
The City of Des Plaines Curb and Sidewalk Program is intended to
repair hazardous sidewalk and curb locations within the
right-of-way. Driveway aprons are not included in the program. The
locations are generated primarily by resident requests, and repaired
after evaluation by the Engineering Department in a "first
come-first serve" order. The purpose of the program is to repair
specific locations of immediate concern, not necessarily entire
blocks or streets. Additional locations will not be added due to
proximity of scheduled and/or budgeted work. These locations will be
added to the inspection list and be completed when budgeting allows.
Any hazardous locations that are unable to be repaired due to
available funds will be temporarily patched by the Public Works
Department until funding becomes available.
EVALUATION NOTES
1. Sidewalks, Carriage walks, and Service walks.
a. Sidewalks with trip hazards, major cracks, significant
spalling and other deterioration should be replaced.
b. Trip hazards are defined as more than 1 1/8" height
differential. A rule of thumb is if you can easily catch your foot
dragging it over the area, the square should be replaced.
c. Major cracks where there is a piece of concrete missing or
the expansion joint has eroded away and a huge gap is left should
be replaced. If there is a small crack (hairline) in the sidewalk
and no settling or spalling has occurred, the walk should not be
replaced. If it appears that further deterioration will occur or
the parkway is beginning to settle, the walk should be replaced.
d. Areas that contain significant spalling or pitting shall be
replaced.
e. Sidewalks being replaced shall be finished to match the
adjacent areas.
i. If matching the adjacent areas results in improper
drainage or new trip hazards, the Engineer shall replace the
surrounding areas as needed. A minimum of one extra square of
sidewalk should be removed and replaced in order to transition
to the correct slope. This includes both service walks in the
parkway and private property.
ii. Replacement of service walks will be allowed up to a
maximum of 6 feet outside the right-of-way. If the condition of
the surrounding area is so poor that this limit needs to be
exceeded, the Engineer shall contact the resident to discuss the
situation.
2. Curbs.
a. Curbs with cracking, settlement, drainage problems, or
significant spalling and other deterioration should be replaced.
Rolled curbs in good condition with no drainage problems will not
be replaced.
b. Cracks in the curb should be replaced only if further
deterioration is likely or there is evidence that the curb might
settle.
c. Curbs that have settled and resulted in obvious low spots
should be replaced. Curbs that have raised up shall also be
replaced.
d. Drainage problems will typically require some survey. The
Engineer shall determine the direction of flow and replace the
area needed. The area may require a catch basin to be installed
and tied into the nearest storm sewer.
e. Most curbs with significant spalling or deterioration have
been damaged by snow plows. Typically large 8-12" pieces of the
curb will be missing and these areas should be replaced. If the
curb is in generally good condition and is missing a short
section, only the missing section should be replaced.
f. New curbs shall be replaced as a depressed curb if the
driveway apron is also being replaced. At locations where the
concrete apron is in good condition, new curbs shall be replaced
as a mountable or rolled curb provided that the flow line is at
the proper elevation to provide positive drainage.
g. New curbs shall be finished to match the existing curb
and/or apron elevations. Curbs replaced on over-laid streets shall
be finished to match the existing curb, and over-laid with the
appropriate thickness of asphalt.
h. Tie bars will be required for integral curb and gutter.
3. Driveway Aprons.
a. Typically, entire driveway aprons will not be replaced.
Depending on the nature and extent of work around the apron and
the existing apron condition, the Engineer may replace the apron
entirely or only partially. This applies to both the curb and
sidewalk work adjacent to the driveway aprons.
b. Apron replacement should be done only if one of the
following conditions is met:
i. The existing driveway apron is old, cracking and
deteriorated to the point where a patch cannot be made such as:
asphalt driveways that are completely alligatored, concrete with
cracks and settlement, or any material that has completely
deteriorated or has obvious drainage problems.
ii. A utility structure such as a sewer manhole, water valve
vault or water service box located within the apron and requires
adjustment.
iii. The entire apron should be replaced where both adjacent
curb and sidewalk are being replaced.
c. New aprons shall be constructed in concrete per current City
standards.
d. Partial apron replacement should be done where the existing
aprons are in generally good condition.
i. For asphalt aprons, approximately 2’ behind the curb or
sidewalk should be repaired (either full depth or surface
removal and replacement). The Engineer will determine the
exact limits for repairs based on the condition of the
driveway. This also applies to repairs on the private side of
the driveway as necessary.
ii. For concrete aprons, the repairs shall extend to the
closest joint (typically 5-6’ behind the curb or walk). If
there is no joint, the Engineer will direct the contractor to
saw cut the limit. Any repair section smaller than 4’ should
be checked for proper drainage and shall not cause additional
bumps or trip hazards.
e. The allowable limit of replacement outside the right-of-way
is 6 feet. If the existing driveway condition is completely
deteriorated, the Engineer shall contact the resident to discuss
the situation.
4. Pavement Patches.
a. Asphalt streets should be repaired to fix any overcuts for
placing curb forms or spalling caused by the removal and
replacement of the curb. Depending on the existing condition of
the street either a full depth patch or surface patch may be
required.
b. Full depth asphalt repairs will require 4" of stone base and
6" asphalt in two lifts. The patch shall be a minimum of 2’ wide,
and extend the entire length of the curb replacement area. All
limits shall be cleanly saw cut.
c. Surface repairs will require only the 2" surface course to
be removed and replaced. Width and length may vary depending on
the extent of surface spalling that occurred when the curb was
removed. This can be used for areas where the curb was removed
cleanly with little or no damage to the existing pavement. Surface
removal can be done by mechanical grinder or saw cut and removed
by hand.
d. For concrete streets with asphalt overlays, the new curb
shall match the existing curb, and the flow line shall be overlaid
for positive drainage. Tie bars shall be drilled and grouted into
the adjacent pavement. If an over cut is necessary, the concrete
shall be poured monolithically with the curb and gutter. Asphalt
shall be overlaid after the concrete has cured.
PRIVATE AND ADDITIONAL WORK
Private work is defined as any work on private property that is
the outside allowable project limits and beyond intent of the
program.
a. The maximum allowable limit to be included in the project
(at no cost to the resident) is 6 feet outside the right-of-way.
Any areas beyond this limit will be considered private work.
b. All private work areas will require the homeowner to acquire
a building permit, hire a licensed contractor, and arrange for
review and inspection through Community Development.
Additional work is defined as areas within the City right of way
that are requested for improvements by a resident but do not qualify
for repairs.
a. If the Engineer determines that the additional work does not
qualify for repairs, the resident will be given the option to pay
for the improvement. The Engineer will prepare a cost estimate
agreement for the resident to sign.
b. If agreed to, the work will be included in the project, and
the City will invoice the resident.
c. No additional work will be performed prior to the agreement
form signed by the resident and received by the Engineer.
Living In Des Plaines |
Your Local Government |
Your City Services
Economic Development
| Online City Reference
Desk
Search |
Site Map |
Home
Send feedback to the City by clicking
here.
Click here to report a website technical issue.
This site is best viewed in
Internet Explorer 7.0 or higher or Firefox 2.0 or higher.
City of Des Plaines
1420 Miner St.
Des Plaines, IL 60016
847-391-5300 |

This site has documents available
in PDF format. If your browser does
not have the Acrobat Reader
plug-in that is required to view
these documents, click here
to
download a free copy of this software. |
Site
Design/Development by
 |
Site
Use Policy
All information © 2008 Des Plaines, Illinois
|