2017 CIP - Contract B – Project Update 7/11/17

All work is weather dependent. Unknown utility conflicts may cause delays.

ON TUESDAY, JULY 11 the contractor will be making a water connection to the existing system at Cora and Campbell. In order to complete this work the water main on Cora from Algonquin to Henry needs to be temporarily shut down. The water shut down is scheduled for July 11 between 9AM and 1PM. Click the link below for more information.

As a result of this work, the intersection at CAMPBELL AVE and CORA ST will be closed to all traffic on 7/11 in order to install new water main and make connections to the existing system.

This week the contractor will continue installing water main on Campbell from Cora to Center.

Testing of the water main on Campbell between River and Cora will take place. The contractor will flush the new main and test it per EPA requirements. Once approved, individual water services will be transferred to the new main. More information will be available soon.

( View PDF )