2017 CIP - Contract B – Project Update 7/17/17

All work is weather dependent. Unknown utility conflicts may cause delays.

This week the contractor will continue installing water main on Campbell from Cora to Center.

The contractor will also begin sanitary sewer repairs at various locations.

Testing of the newly installed water main on Campbell will continue.  The contractor will flush the new main and test it per EPA requirements. Once approved, individual water services will be transferred to the new main. More information will be available soon.