2017 CIP - Contract B – Project Update 8/7/17

All work is weather dependent. Unknown utility conflicts may cause delays.

On WEDNESDAY, AUGUST 9 the contractor will begin storm sewer installations, repairs and replacements at various locations on CAMPBELL. Click the link below for the resident notification.

On WEDNESDAY, AUGUST 9 and THURSDAY, AUGUST 10, the intersection at CENTER and CAMPBELL will be closed to all traffic between the hours of 7AM and 5PM to complete the storm sewer work at this location.

The contractor will continue water main installation on WEST VILLA.

( View PDF )