News Details

2017 CIP - Contract B – Project Update 8/14/17

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

The contractor will continue storm sewer installations, repairs and replacements at various locations on CAMPBELL.

On TUESDAY, AUGUST 15 and WEDNESDAY, AUGUST 16, the intersection at CAMPBELL and WHITE will be closed to all traffic in order to install new storm sewer.

This week, the contractor will begin the roadway construction phase on CAMPBELL. More information will be available soon.

WEST VILLA:

The contractor will continue storm sewer installations, repairs and replacements at various locations on WEST VILLA.

On TUESDAY, AUGUST 15, the contractor will begin work on transferring existing water services to the new water main.  The contractor anticipates transferring 6-8 services per day.  It will take approximately 10 days to transfer all services.  All work is weather dependent and unknown utility conflicts may cause delays.  Click the link below for the resident notification.

( View PDF )