2017 CIP - Contract B – Project Update 10/4/17

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

The contractor will continue miscellaneous clean up on CAMPBELL.

The contractor will continue placing topsoil on CAMPBELL. The contractor will continue placing sod.

WEST VILLA DR:

The contractor will continue concrete work on the east side of WEST VILLA. The contractor will also begin grading parkways and project clean up.

FIRST AVE:

The contractor will continue concrete work on FIRST.

BROWN ST:

The contractor will continue work on transferring water services to the new water main.

The contractor will continue storm sewer installation and repairs on BROWN.

On THURSDAY, OCTOBER 5, the contractor will be making a water main connection and repair at the intersection of BROWN ST and LEE ST. In order to complete the work the water system on LEE ST between BROWN ST and PERRY ST must be temporarily shut down. THE WATER MAIN IS SCHEDULED TO BE SHUT DOWN ON OCTOBER 5 BETWEEN 6AM AND 10AM.