News Details

2017 CIP - Contract B – Project Update 10/9/17

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

The contractor will continue placing topsoil and sod on CAMPBELL. 

On MONDAY, OCTOBER 9, the contractor will mill the CAMPBELL intersections at CENTER, CORA and WHITE in preparation for final asphalt surface paving. It is anticipated the surface will be paved later this week. More information will be available soon.

WEST VILLA DR:

The contractor will continue miscellaneous project clean up and grading parkways on WEST VILLA.

It is anticipated that the base course of asphalt pavement will be paved later this week on WEST VILLA. More information will be available soon.

FIRST AVE:

The contractor will continue concrete work on FIRST.

BROWN ST:

On TUESDAY, OCTOBER 10, the contractor will begin the roadway work on BROWN. As part of this phase, all pavement, all curb, all driveway aprons, and sidewalks indicated in spray paint will be removed. After removing the pavement, curb and sidewalks, the contractor will excavate for the pavement base. Then a new stone base will be placed and graded. Click on the link below for the resident notice.