2017 CIP - Contract B – Project Update 10/10/17

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

The contractor will continue placing topsoil and sod on CAMPBELL.

On TUESDAY, OCTOBER 10, the contractor will mill the CAMPBELL intersections at CENTER, CORA and WHITE in preparation for final asphalt surface paving. This work was rescheduled from 10/9.

It is anticipated the surface will be paved on CAMPBELL later this week. More information will be available soon.

WEST VILLA DR:

The Contractor will begin placing and grading the stone base and paving the asphalt base pavement on West Villa on Wednesday, October 11. The contractor anticipates this phase of work will take approximately 3 days, with a tentative schedule as follows:

On WEDNESDAY 10/11 the contractor is scheduled to rough grade the stone base. Additional stone material will be delivered, placed and graded. Driveway ramps may be removed during this phase. We recommend that you remove any vehicles you will need to use during this period.

On THURSDAY 10/12 the contractor is scheduled to place and grade the stone base. Remaining driveway ramps will be removed during this phase. We recommend that you remove any vehicles you will need to use during this period.

On FRIDAY 10/13 the contractor is scheduled to pave the asphalt base pavement.

Click the link below for the notification letter.

FIRST AVE:

The contractor will continue concrete work on FIRST.

BROWN ST:

On TUESDAY, OCTOBER 10, the contractor will begin the roadway work on BROWN. As part of this phase, all pavement, all curb, all driveway aprons, and sidewalks indicated in spray paint will be removed. After removing the pavement, curb and sidewalks, the contractor will excavate for the pavement base. Then a new stone base will be placed and graded.