2017 CIP - Contract A – Project Update 11/3/17

Lee

The contractor has set up traffic control for this project. They plan to begin work on constructing new water valve vaults on Wednesday, November 8, which is the earliest the Canadian National Railroad could provide a railroad flagger to the contractor. The contractor will continue to work to prepare for the augering and jacking of a new 12” water main under the railroad tracks, which is scheduled for November 15-17. The existing water main has a leak and requires full replacement.