Construction & Traffic Updates

Des Plaines Construction & Traffic Updates

Road Construction Image


2017 CIP - Contract B – Project Update 6/19/17

June 17, 2017 

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

The contractor will continue tree removals.

ON TUESDAY JUNE 20, the contractor will begin construction of the new water main on Campbell Avenue. A few days of preparatory work will take place including equipment mobilization, material delivery, saw cutting pavement, and pavement removal. Pipe installation is anticipated to begin on Thursday June 22.

The contractor will begin at Campbell and River Rd and proceed to the west to Center St. It is anticipated this phase work will take approximately 20 days.

Click the link below for the resident notice.

View PDF Read More »

2017 Concrete Improvements

June 15, 2017 

Attention: Residents along Yale Court

Please note that 3 hour parking enforcement along Yale Court will be going back into effect. Please be aware of the signage when parking near your property.


2017 CIP - Contract B – Project Update 6/14/17

June 14, 2017 

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

The contractor will begin tree removals starting on 6/15. It is anticipated this work will take 3-4 days.

It is anticipated the contractor will begin installing water main late next week. More information will be available soon.

Read More »

Road Closures at Union Pacific Railroad Crossings

June 12, 2017 

The Union Pacific will be repairing various railroad crossings that require road closures or periodic stopping of traffic.

The following streets will be completely closed to traffic:

Howard Ave 6/11 through 6/14 PM (Closure)

Oakton Ave 6/11 through 6/14 PM (Closure)

Rand Rd 6/12 through 6/14 PM (Closure)

Please follow the established detour routes posted on site.


The following crossings will have flaggers present to stop traffic periodically to complete repairs:

Touhy Ave 6/10 through 6/12 (Flagging)

Mount Prospect Rd 6/10 through 6/12 (Flagging)

Algonquin Rd 6/11 through 6/14 (Flagging)

Thacker St 6/12 through 6/14 (Flagging)

Wolf Rd 6/12 through 6/14 PM (Flagging)

River Rd 6/12 through 6/14 (Flagging)

E. River Rd 6/14 through 6/16 (Flagging)


Below are the IDOT press releases for more information on the Oakton and Rand crossings:




Read More »

2015 Contract B - Algonquin Road Sewer Project

June 7, 2017 

ON THURSDAY JUNE 8, the contractor will be relocate water main that is in conflict with the sewer installation. In order to complete this work, the water main system on Devonshire Drive from Elmhurst Rd to Susan Dr must be temporarily shut down.

THE WATER SHUT DOWN IS SCHEDULED FOR:

THURSDAY, JUNE 8, 2017

BETWEEN THE HOURS OF 8:30 AM AND 1:00 PM

The Contractor will be working diligently to make the connections as quickly as possible. As soon as the work is complete, the water main and your water service will be turned back on.

View PDF Read More »

Archives...