Construction & Traffic Updates

Des Plaines Construction & Traffic Updates

Road Construction Image


2017 CIP - Contract B – Project Update 11/16/17

November 15, 2017 

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

The contractor will continue miscellaneous project clean up on CAMPBELL.

WEST VILLA DR:

The contractor will continue placing topsoil and sod on WEST VILLA.

FIRST AVE:

The contractor will continue miscellaneous project clean up on FIRST.

Topsoil and sod restoration is anticipated to begin within the next two weeks. More information will be available soon.

BROWN ST:

The Contractor has scheduled the work for placing the surface layer of asphalt pavement Friday, November 17 through Tuesday, November 22. Click the link below for more information.

View PDF Read More »

2017 CIP - Contract A – Project Update 11/3/17

November 3, 2017 

Ardmore

The paving subcontractor (Arrow Road Construction) has completed the process of grading the gravel road base for the first layer of asphalt pavement. They will pave the first layer (4”) of asphalt pavement on Friday, November 3. You will be able to drive on the new asphalt Friday evening. The next step will be to adjust any manholes in the pavement to the finished pavement elevation. After that, the contractor can pave the final layer (2”) of asphalt pavement. Topsoil placement and sodding will then be completed.

Drake

The concrete subcontractor, JG Demo, has completed pouring curb and driveway aprons from Pinehurst to Amherst (inside curve). Once the concrete successfully passes the laboratory strength test, the contractor will remove driveway access from the outside curve of Drake. I estimate this will occur on either Tuesday or Wednesday of next week.

The paving subcontractor (Arrow Road Construction) has completed the process of grading the gravel road base for the first layer of asphalt pavement from Ardmore to Wolf. They will pave the first layer (4”) of asphalt pavement from Ardmore to Wolf on Friday, November 3. You will be able to drive on the new asphalt Friday evening. The next step will be to adjust any manholes in the pavement to the finished pavement elevation. After that, the contractor can pave the final layer (2”) of asphalt pavement. Topsoil placement and sodding will then be completed

Cranbrook

The concrete subcontractor, JG Demo, has completed pouring curb and driveway aprons from Mt Prospect Road to Drake (north side). Once the concrete successfully passes the laboratory strength test, the contractor will remove driveway access from the south side of Cranbrook. I estimate this will occur on either Tuesday or Wednesday of next week.

Click on link for update on Lee Street

Read More »

2017 CIP - Contract B – Project Update 11/2/17

November 2, 2017 

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

The contractor will continue miscellaneous project clean up on CAMPBELL.

WEST VILLA DR:

The contractor will continue miscellaneous project clean up on WEST VILLA.

Topsoil and sod restoration is anticipated to begin within the next two weeks. More information will be available soon.

FIRST AVE:

The contractor will continue miscellaneous project clean up on FIRST.

Topsoil and sod restoration is anticipated to begin within the next two weeks. More information will be available soon.

BROWN ST:

The Contractor has scheduled the work for placing and grading the stone base and paving the asphalt base pavement on BROWN to start on Friday, November 3. The contractor anticipates this phase of work will take approximately 2 days, with a tentative schedule as follows:

On FRIDAY 11/3 the contractor is scheduled to rough grade the stone base. Additional stone material will be delivered, placed and graded. Driveway ramps will be removed during this phase. We recommend that you remove any vehicles you will need to use during this period.

On MONDAY 11/6 the contractor is scheduled to pave the asphalt base pavement.

Click the link below for more information.

View PDF Read More »

2017 CIP - Contract B – Project Update 10/31/17

October 31, 2017 

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

The contractor will continue miscellaneous project clean up on CAMPBELL.

WEST VILLA DR:

On WEDNESDAY, NOVEMBER 1, the contractor is scheduled to pave the surface course of pavement on WEST VILLA. Click the link below for more information.

W VILLA - pavement surface

FIRST AVE:

On WEDNESDAY, NOVEMBER 1, the contractor is scheduled to pave the surface course of pavement on FIRST. Click the link below for more information.

FIRST - pavement surface

BROWN ST:

The contractor will continue concrete work on BROWN.

It is anticipated the contractor will pave the base course of asphalt pavement on BROWN late this week or early next week. More information will be available soon.

Read More »

2017 CIP - Contract B – Project Update 10/30/17

October 30, 2017 

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

The contractor will continue miscellaneous project clean up on CAMPBELL.

WEST VILLA DR:

The contractor will pave the surface course of pavement on WEST VILLA within the next two weeks. More information will be available once the schedule is finalized.

FIRST AVE:

The contractor will pave the surface course of pavement on FIRST within the next two weeks. More information will be available once the schedule is finalized.

BROWN ST:

The contractor will continue concrete work on BROWN.

Read More »